GACHSARAN (NIPNA) – The Gachsaran Heavy Polyethylene Project is gearing up to enter its installation phase, following significant progress in engineering and equipment manufacturing.

According to the Public Relations Office of Gachsaran Polymer Industries, the overall progress of the project reached 41.13% as of February 4, with engineering progress advancing to 82.57%.

The report noted that the construction of the reactors for the project has been completed, and final tests are underway. With these developments, the installation of fixed equipment is expected to commence shortly, accelerating the pace of the project’s implementation.

The Gachsaran Heavy Polyethylene Project, a key initiative in Iran’s petrochemical sector, aims to enhance domestic production capacity and meet growing demands for high-density polyethylene. The project's swift progress highlights the country’s efforts to strengthen its industrial base and promote self-sufficiency in the petrochemical field.