News Agency - Detail

Progress of Almas Mahshahr Petchem Project Reaches 11% Completion

Progress of Almas Mahshahr Petchem Project Reaches 11% Completion
(Wednesday, November 27, 2024) 15:08

MAHESHTAN (NIPNA) – The Almas Mahshahr Petrochemical Project, a flagship undertaking of the Persian Gulf Petrochemical Industries Company (PGPIC), has achieved 11% progress, marking a significant milestone in its development, according to project CEO Mehdi Qarouni.

Speaking on Wednesday, Qarouni revealed that foundational engineering and equipment procurement were completed last year, with construction beginning in December 2023 after obtaining environmental permits.

“The site preparation was a major challenge,” Qarouni said. “A portion of the project land was originally marshland. To prepare it, we conducted extensive groundwork, including excavating over 121,000 cubic meters of soil, equivalent to 6,000 truckloads, and removing 813 truckloads of debris from the site.”

Major Construction Milestones

To date, 70 kilometers of piling have been completed, along with the foundation work for seven out of ten cylindrical storage tanks. Construction on the base and walls of three tanks is underway, while work on three additional tanks will commence mid-December. Structural installations for two warehouses and a central workshop have also been completed, with masonry work in progress.

One critical aspect of the project has been securing utilities for the massive industrial complex. Qarouni announced the signing of a long-term agreement between Almas Mahshahr and Fajr Energy Gulf Petrochemical Company for the provision of utility services, following detailed engineering and consumption studies.

Tackling Supply Chain Challenges

Amid sanctions and logistical hurdles, the project team has successfully ordered key delayed-delivery equipment, including furnaces, compressors, reactors, and storage tanks, from domestic and international manufacturers. Valued at approximately $180 million, these orders include dual-walled, spherical, and atmospheric storage tanks, cooling towers, and other critical components.

“Thanks to the shareholders' financial contributions, around 30 trillion Iranian rials have been spent, with additional funding commitments underway to sustain momentum,” Qarouni said.

Progress on Phase Two

Plans for the project's second phase are advancing steadily. This phase will include a polypropylene unit and two polyethylene production facilities. Land allocation for the northern section of the site is in its final stages, pending approval from the Supreme Council of Special and Free Zones. Geotechnical studies have been completed, and tender documents for land preparation have been distributed.

Infrastructure work for pipelines to transport feedstock and products between Bandar Imam Petrochemical and the second-phase site has also begun. Additionally, a memorandum of understanding with the National Petrochemical Company and an Italian partner has secured technical expertise for downstream polymer production.

The Almas Mahshahr project is a cornerstone of PGPIC's strategy to enhance Iran's petrochemical output, reinforcing its position as a regional industrial hub despite challenging economic conditions.

Email is required
Characters left: 500
Comment is required